Margalla Road Extension Delay Threatens 2026 Deadline
Margalla Avenue’s extension has reached 43%, but slow progress is raising concerns as officials push for more workers and machinery before 2026.

Margalla Avenue’s extension is still moving, but the pace has clearly become a concern. The project is being reported at 43% progress in a November 23 CDA update cited by secondary reporting, while the wider reporting still points to a December 31, 2026 completion target. After a November 26 inspection, Mohsin Naqvi reportedly asked officials to add more workers and machinery, which tells you this is not yet a smooth run to the finish.
What are the latest Margalla Road extension figures?
The project is the Margalla Avenue extension from the N-5 corridor toward the M-1 Motorway, along with the Sangjani Interchange. APP reported 35% completion on November 8 and 36% on November 13, while later reporting cited a November 23 CDA update that placed progress at 43% (APP, November 8, APP, November 13, a source report). For background, read our earlier coverage: Rawalpindi Ring Road Delay Reaches Ninth Postponement.
That jump does not mean 43% of the road is open for traffic. It refers to overall reported project progress, which can include different parts moving at different speeds.
What has been built, and what work remains?
The reports say the project includes main road work, service roads, loops, ramps, an underpass, bridge-related work near N-5, the Sangjani Interchange foundation and piling, and drainage works such as culverts. APP’s earlier reports also noted that four of five culverts had been completed.
So, yes, progress is real. But the key point for drivers is simple: a partly built road is not the same as a usable route. Until the ramps, bridge sections, interchange work and safety-related pieces are done and officially opened, this link cannot serve the traffic it is meant to carry.
If you want more background on nearby road work in the city, our Margalla Underpass on Islamabad Park Road Opening Soon report gives a useful sense of how these Islamabad projects usually move from construction to opening.
Why did Mohsin Naqvi order faster construction?
On November 26, Naqvi reportedly inspected the site and directed officials to increase both workers and construction machinery. The same report says he was worried the existing pace was too slow for the reported December 31, 2026 target, and he asked for daily progress updates with another inspection after seven days (a source report).
That matters because this is not just a beautification project. If labour and equipment stay limited, the schedule pressure will only grow. And for a road link like this, delays tend to hit commuters twice: first during construction, then again if the promised relief takes longer to arrive.
How could the completed project affect Islamabad drivers?
If finished as planned, the extension should give Islamabad another route toward the M-1 Motorway and improve access for people coming from Khyber Pakhtunkhwa. The reports also describe it as a future route that could help with access toward Islamabad International Airport.
But that benefit is still conditional. Right now, the road is still under construction, and no report in the supplied coverage says it has opened for normal traffic. So if you’re planning travel around Islamabad today, keep using the routes already open to you.
Can the December 31, 2026 deadline still be met?
The reports still cite December 31, 2026 as the target, and no revised date was mentioned in the supplied coverage. At the same time, the November 26 inspection shows that the pace is under pressure and needs to improve fast.
So the honest answer is this: the deadline is still the one being talked about, but it should not be treated as guaranteed. The next seven-day inspection and the next CDA progress update will be the best clues about whether the work is actually picking up.
What should Islamabad residents watch next?
Keep an eye on these points:
- the result of the next inspection after seven days,
- any new CDA progress figure and the date it covers,
- more workers or machinery being added on site,
- progress on Sangjani Interchange ramps, piling and bridge work,
- completion of the remaining drainage and culvert work,
- any formal update that changes the December 31, 2026 target,
- and any official opening notice before assuming the route is usable.
For now, the Margalla Avenue extension still looks strategically important, but it is also under real schedule pressure. The target date remains part of the reporting, yet the work clearly needs faster movement before anyone should count on it as a finished escape route for Islamabad traffic.
Conclusion
The big takeaway is simple: the Margalla Avenue extension may still meet its reported December 31, 2026 target, but the pace of work has become a concern and the project is not ready for traffic yet. For Islamabad commuters and travellers from Khyber Pakhtunkhwa, the smartest move is to wait for the next CDA update and the follow-up inspection before expecting any relief from this route.
Explore DrivePK services
Buying or selling a vehicle? Explore DrivePK services, including car inspection, Sell It For Me and Featured Listings, and choose the option that fits your needs.
For more updates, visit DrivePK.com
Share this article
About the author

Dr Khan
Automotive expert and content strategist



Comments (0)
Sign in required
Sign in to comment on this article.
No comments yet. Be the first to share your thoughts!